Menu
Previous article :
VSL installed 3 pairs of viaduct deck segments in a single day at HS2!
Next article :
VSL tackles the bearing replacement market in Hong Kong
  • Imprimer

Vert-de-Maisons, located between Alfortville and Maisons-Alfort, is one of the four underground stations of batch T2A of line 15 South of the Grand Paris Express transit system. As part of the Horizon consortium, Bouygues Travaux Publics is responsible for the civil engineering works.

A 40-meter-deep cavern

Comprising eleven levels, including nine underground, the station lacked the volume required to accommodate all of the platforms and passenger access corridors. To address this issue, the tunnel had to be widened: two lateral galleries, each 65 meters long, were therefore created either side of the tunnel, forming a cavern

Freezing the ground for safe tunnel excavation

The next step? The excavation of the mezzanine corridors intended to accommodate escalators and provide access to the platforms. This is where ground freezing comes in. This cutting-edge technique, monitored via sensors, consists in increasing the mechanical resistance of the surrounding ground and making it impermeable, by freezing the water naturally present within the soil to ensure safe tunnel excavation.

Teams launched these exceptional operations at the end of 2022 to enable the currently ongoing excavation of these tunnels, using traditional methods. Each manoeuvre is meticulously planned and particularly complex due to the gradient of the site. 

In the station cavern, the completion of lining concrete operations and dismantling of provisional installations enabled civil engineering teams to access level -9 and set about building the platforms, before moving on to the internal structures higher up (between levels -6 and -9). Completion of this crucial stage of the project will be a major milestone, giving teams from the Colas Rail-Alstom consortium access to the site to lay the rail tracks.

Zoom
Zoom
Zoom

The art of coordination

In parallel with the operations carried out by the Horizon consortium, the contracting client wanted the architectural and technical finishing work batches (Equans) to be launched early on those levels where progress made it possible to do so. As site manager, the consortium is responsible for coordinating these various activities. 

With batch T2A in full swing, more than 100 people are currently mobilised. The Horizon consortium will have completed its work on the station by the end of 2023, and the facility is due to go live at the end of 2025.

The Grand Paris Express project
South of the capital, line 15 South is just one component of the largest urban project underway in Europe, the Grand Paris Express transit system. Line 15 South, which will run between Pont de Sèvres and Noisy-Champs, crossing 22 municipalities and four départements, is divided into eight batches, three of which have been handled by the consortium led by Bouygues Travaux Publics (T2A, T3A and T3B).

In total, 68 stations and four new lines representing a network of 200 kilometres will be commissioned by 2030, enabling passengers to travel more easily and quickly between each suburb, without having to transit through Paris itself. 


 
  • Imprimer
Access all content :
Log in to view all articles, to comment, or customise your filters.
Log in
Read also :
Articles suivants
Special topic
THE BENEFITS OF BEING A SMART, RESILIENT REGION IN THE FACE OF THE CRISIS
Special topic
The Health & Safety strategy of Bouygues Travaux Publics
Special topic
Campus: where will our children learn tomorrow?
Special topic
Lean management is making its way onto Bouygues Construction work sites
Next topic :
All news